All the construction and infrastructure work of the power plant’s offices, halls, command floor, guardhouse, as well as regional graffiti and drawing applications of the power plant were done by us.
GUARDHOUSE
All the construction and infrastructure work of the security unit of the power plant main entrance gate, consisting of an area of 100 m2, were carried.
CONTROL FLOOR
The rearrangement of the main control room, which consists of an area of 200 m2, the facade work and the supply of furniture were done.
OFFICE
Reorganization of the existing 2-storey office building consisting of 900 m2 area, designing an additional 100 m2 building, acoustics, lighting and furniture supplies.
All the works for the rearrangement of the 900 m2 existing and 2-storey office building of the power plant, the design of an additional 100 m2 building, acoustics, lighting and furniture were made by ABBA Architecture. Custom furniture designs were prepared and manufactured. All decoration works of the areas were also done by ABBA.
TURNA HALL
All construction and infrastructure works have been completed in the social facility of Enerjisa Üretim Bandırma Power Plant, in the Turna Hall of a total area of 200 m2, including 150 m2 closed area and 50 m2 open area. Architectural design, implementation, control works and consultancy were carried out during the construction. All furniture supplies of the office were made, custom furniture designs were prepared and manufactured. All decoration works of the office were also done by ABBA.
Turnkey Project
Bandırma, Balıkesir, Türkiye